Responding to an RFI Action
Status: Open
Role: Responder
As the Responder, you are responsible for reviewing the action, providing the required response, and closing the action once the work has been completed.
Available actions
• Assign Responders
• Close Comment
• Escalate
• Edit Action
• Respond
Responding to and closing an action
-
Open the relevant RFI Action and select the appropriate option from the Actions menu to review or update the details.
-
Add any additional information required.
-
Select Respond to enter your response to the action.
-
Once the response has been provided and the action is ready to be closed, select Close Comment.
-
Complete the required closure details in the pop-up window and confirm the closure.
Important: All RFI Actions must be closed before the associated RFI can be closed.